Commercial Fit Outs Perth: End of Trip Facilities

Prominently positioned on the corner of Hay Street and Outridge Crescent in Subiaco, a ground floor tenant of the office building was in need of brand new End of Trip Facilities. Jewelbic Plumbing & Gas carry out commercial fit outs Perth businesses can rely on, and we were able to complete this project ahead of schedule, in 14 weeks.

Shop fitouts Perth companies can call upon to achieve tight deadlines without compromising on quality.

Project scope:

To remove existing male and female bathroom facilities on the ground floor of the building and extend into large high end, end of trip facilities. New male, female and unisex accessible facilities with with showers, changing rooms, lockers, toilets and basins. As well as a plant room for the hot water plant which consists of 2x Stiebel Heat Pump system.

Scanning and coring of new penetrations for the new waste water system which was installed in the basement car park below. All new hot and cold water system through out. Relocating fire services. Final touches and smoothing of features you’d expect from the best commercial fit outs Perth has to offer.

Unique solutions:

Jewelbic Plumbing & Gas went above and beyond the call of duty to achieve the following outcomes.

  1. Project completed ahead of schedule, from start to finish in 14 weeks
  2. Also assisted with maintenance issues on the building at the same time as the construction, thanks to our expertise in both commercial fit out, construction and commercial maintenance
  3. Prevented drainage downtime by performing the new drainage installation in the basement car park whilst it was still functioning
    • Adhered to facility management procedures as expected during the best commercial fit outs Perth can offer
    • Safely cordoned off areas with correct signage and barricades for both cars and pedestrians

The process:

  • Decommission existing male and female toilets
  • Mark out new drainage core holes
  • Scan and core new penetrations in concrete
  • Install new under slung waste water system with fire protection collars
  • Install new water service system
  • Install new tap ware fixtures and hot water plant
  • Test and commission
  • Draw and submit as-constructed drain plans and operation and maintenance manuals

Commercial Fit Outs Perth: Commence Your Project

Shop fitouts Perth businesses can call on for quick turnaround and quality workmanship. Contact us today to commence your commercial fit out project.

CLIENT:
Ascent Construction

PARTNERS INVOLVED:
Reece, Galvin

PROJECT DURATION:
June 2019 – Aug 2019

TOTAL BUILD:
$600,000.00